Facts & figures

Drinking water production indicators and key figures for SNDE infrastructure.

Latest bulletin · August 2026

Aftout Es-Saheli water production – August 2026

Normal production despite record turbidity

Average production in August
147,000–150,000m³ per daySatisfactoryThe system’s maximum capacity
Turbidity removal efficiency
100%SatisfactoryStable throughout the month
Highest turbidity in August
4,568NTUHigh levelRecord level measured on 8 August
Latest turbidity reading
1,780NTUHigh levelAbove 1,000 NTU since 21 July

Since 21 July, raw-water turbidity at the Aftout Es-Saheli intake has exceeded 1,000 NTU. Despite this rise, which reached record levels in August, the system kept its normal production throughout the month, between 147,000 and 150,000 m³ per day.

Raw-water turbidity at the intake (NTU)Turbidity measures the particles suspended in river water. The higher it is, the more treatment the water needs.
Show the data as a table
ReadingValue (NTU)
Highest turbidity in AugustRecord level measured on 8 August4,568
Latest turbidity readingAbove 1,000 NTU since 21 July1,780
Reference — Threshold exceeded since 21 July1,000

Landmarks

Key figures for our infrastructure

SNDE founded when SONELEC was split in two
2001
Transfer main from Aftout to Nouakchott
≈ 200 km

Strengthening the Idini wellfield

  • 24 new wells in the Idini wellfield
  • 37 wells to be rehabilitated
  • Two new reservoirs with a total capacity of 7,500 m³
  • 59 km of 1,200 mm water transmission pipes
  • Well equipment and connection to a remote operation and management system

Water pumping and distribution hub – Nouakchott North

Works completed25%
Total cost
MRU 800,000,000
Schedule
18 months
  • Supply and installation of a 1,000 mm steel transmission main over 10 km
  • Supply and installation of an 800 mm steel distribution main over 2.1 km
  • Supply and installation of a second 500 mm steel distribution main over 7 km
  • Construction of two reservoirs of 5,000 m³ each
  • A booster pumping station with a capacity of 1,800 m³ per hour
  • Construction of a 1,200 m³ water tower, 35 m high

Aftout Es-Saheli system

  • Water intake on the Senegal River
  • Treatment plant, including a turbidity removal unit
  • Pumping stations and a transfer main of about 200 km
  • Output of 147,000 to 150,000 m³ per day in August 2026, the system’s maximum capacity

Earlier bulletins

Earlier bulletins will appear here as they are published.

SNDE publishes production bulletins from the site’s admin panel. Each new bulletin takes this place at the top of the page, and the previous one moves to the archive.

Need help?

Customer service can answer your questions about your subscription, your bills and water supply.